AI's limit is power.
Demand for power has outrun the grid, so AI data centres look for a faster way in or build their own. Every way around the grid has its own queue: the equipment makers, the turbine makers, the winter night and the reactors' fuel. This journal follows that one problem in seven chapters, from the grid connection to the reactor, from primary sources.
Read the chapters in order, or follow the power stop by stop.
-
Chapter 1 · The grid connection
- Johor and SingaporeThe plug, not the chip, decides who gets to build
- Malaysia is not alone. In America, the grid now decides who waits, who is cut first and who pays.
-
Chapter 2 · The grid connection
- America rations the plugWho may be cut, who must hold on, who pays
- The grid cannot simply build its way out, because its machines come from a few factories.
-
Chapter 3 · Transformers and switchgear
- The equipment queueTransformer and switchgear makers are building to keep the wait, not to end it
- So builders skip the grid and make their own power, and meet the turbine makers' queue instead.
-
Chapter 4 · Power beside the site
- Building your own powerGE Vernova's queue, not the grid's, sets the date
- GE Vernova is now selling heavy gas turbine places for 2032. Why not build solar and batteries, the fastest power there is?
-
Chapter 5 · Power beside the site
- Solar and batteriesFast to build, but short of a winter night
- They are fast, but the grid counts them as a fraction of a firm megawatt, so buyers turn to power that runs all year: reactors.
-
Chapter 6 · Nuclear power
- Nuclear for AIThe old reactors come first because they already own the hard parts
- Old reactors go first. The new ones are small, and their fuel is the gate.
-
Chapter 7 · Nuclear power
- MicroreactorsThe reactor is the easy part, the fuel is the gate
- The reactor is the easy part. Every route to the next gigawatt for AI runs through a queue.
Or follow the power, stop by stop.
Chapter 1 · Johor and Singapore
It starts with a wire
Power for an AI data centre arrives over high-voltage lines from the public grid. In Johor and Singapore, the right to draw that power, not the supply of chips, now decides who gets to build.
Chapter 2 · America rations the plug
The grid rations the plug
High-voltage power arrives from the public grid through a substation built for the site. In America the grid now decides who waits, who is cut first and who pays.
What binds. The wait for a connection now runs to years, and the grid decides who is served first.
Chapter 3 · The equipment queue
The machines at the gate
Transformers step the voltage down at the grid and switchgear routes and protects it inside the fence; a handful of makers build them.
Chapter 3 · The equipment queue
Built to order, not to stock
Nothing switches on without them, and they are made in a handful of factories, so the grid cannot simply build its way out.
What binds. The makers add factories only as fast as signed orders justify, so the wait is kept, not cleared.
Chapter 4 · Building your own power
So build power next door
Builders skip the grid and make their own power beside the building: gas turbines, engines and fuel cells.
Chapter 4 · Building your own power
And meet the turbine queue
The heavy gas turbine is the core machine, and its makers are selling slots in 2032.
What binds. Skipping the grid queue means joining the turbine makers' queue instead.
Chapter 5 · Solar and batteries
The fastest power there is
Solar farms and batteries are most of what America planned to build in 2026. A battery takes about a year, a solar farm about two, and nobody waits in the turbine makers' queue.
Chapter 5 · Solar and batteries
But not through a winter night
An AI data centre draws nearly the same power at 3am as at 3pm. PJM counts a megawatt of tracking solar as 7 per cent of a firm one, and a four-hour battery as 57 per cent.
What binds. A four-hour battery reaches the evening, not the night, so buyers turn to power that runs all year.
Chapter 6 · Nuclear for AI
Power that runs all year
Existing reactors, restarted or upgraded, sell power to AI campuses first; new and micro reactors follow.
Chapter 7 · Microreactors
The reactor is the easy part
Microreactors are small enough to build in a factory and drive to a site. What paces them is the fuel, not the machine.
What binds. Most new reactors need a richer fuel, HALEU, that America makes on one demonstration line.
The whole chain
Every answer is a queue
The grid, the machines at the gate, the turbines, the winter night and the reactors' fuel: each way to the next gigawatt for AI has a queue of its own. The slowest one sets the date.